Building permits in Seattle are issued by the Seattle Department of Construction & Inspections (SDCI)1. You can apply and request inspections online through services.seattle.gov2.

Last checked

On this page
  1. Building department contacts
  2. Do you need a permit in Seattle? Common projects
  3. Building codes in force in Seattle
  4. Seattle building permit fees
  5. How to get a building permit in Seattle
  6. Permit expiration and extensions
  7. Inspections in Seattle
  8. Building without a permit in Seattle
  9. Doing the work yourself (owner-builder)
  10. Washington rules that also apply in Seattle
  11. Sources

Building department contacts

Seattle Department of Construction & Inspections (SDCI)1

Building permits

Address
700 5th Ave, Suite 2000, Seattle, WA 98104 (mailing: P.O. Box 34019, Seattle, WA 98124-4019)
1
Hours
Most staff 8 AM - 4 PM (phone or email)3
Inspections
Online, or 24-hour line (206) 684-89004

SDCI Code Compliance3

Code enforcement

Public Health – Seattle & King County, Plumbing and Gas Piping Program6

Health department

Apply online
kingcounty.gov6
Phone
(206) 263-9566 (Downtown Seattle)6
Address
401 5th Ave., Suite 1100, Seattle, WA 98104 (mailing)
5
Hours
Mon, Wed, Fri 8 am to 3 pm; Tue, Thu 10:30 am to 3 pm6

To look up permits already issued for an address (useful before you buy, or to check a contractor's work), use the city's official permit search: services.seattle.gov7.

Do you need a permit in Seattle? Common projects

Each project below has its own page with Seattle's exact rule, the official wording, fees and inspections.

ProjectPermit needed?Key limit in the city rule
FenceDepends on size or scopeExempt up to this height: 8 feet8
DeckDepends on size or scope–
ShedDepends on size or scopeExempt up to this area: 120 square feet9
RoofDepends on size or scopeLike-for-like replacement exempt? Yes8
PoolYes–
Water heaterYes–

Building codes in force in Seattle

These are the model codes Seattle enforces, with the edition and the date it took effect. Plans are reviewed and work is inspected against them. For the state framework, see Washington building codes.

CodeTitle as adoptedModel editionEffective
International Residential Code (IRC)2021 Seattle Residential Code1020211011
International Building Code (IBC)2021 Seattle Building Code1220211211
International Existing Building Code (IEBC)Seattle Existing Building Code (2021 IEBC base)1320211311
International Mechanical Code (IMC)Seattle Mechanical Code (2021 IMC base)1420211411
International Fuel Gas Code (IFGC)Seattle Fuel Gas Code (2021 IFGC base)1520211511
Uniform Plumbing Code (UPC)2021 Seattle Plumbing Code1620211611
National Electrical Code (NEC)2023 Seattle Electrical Code17202317–

Seattle building permit fees

Fees come from the 2026 Fee Subtitle – Seattle Municipal Code Chapter 22.90018, effective 18.

How valuation is set. Project value → Development Fee Index (Table D-1); Table D-2 sets permit and plan review fees as % of DFI18.

Each line is worded as in Seattle’s schedule; formulas are not added up into a total (how permit fees work).

FeeTypeAs the schedule states it
SDCI base feeFlat fee$29218
Technology feeTechnology surcharge5% of all fees18
Development Fee Index $0 to $1,000Based on project valuation$0 to $1,000 $325 for the first $1,000 of value or fraction thereof18
Development Fee Index $1,001 to $25,000Based on project valuation$1,001 to $25,000 $325 for the first $1,000 of value plus $1.60 for each additional $100 of value or fraction thereof18
Development Fee Index $25,001 to $50,000Based on project valuation$25,001 to $50,000 $709 for the first $25,000 of value plus $1.55 for each additional $100 of value or fraction thereof18
Development Fee Index $50,001 to $75,000Based on project valuation$50,001 to $75,000 $1,096.50 for the first $50,000 of value plus $1.50 for each additional $100 of value or fraction thereof18
Development Fee Index $75,001 to $100,000Based on project valuation$75,001 to $100,000 $1,471.50 for the first $75,000 of value plus $1.40 for each additional $100 of value or fraction thereof18
Development Fee Index $100,001 to $175,000Based on project valuation$100,001 to $175,000 $1,821.50 for the first $100,000 of value plus $7.75 for each additional $1,000 of value or fraction thereof18
Development Fee Index $175,001 to $250,000Based on project valuation$175,001 to $250,000 $2,402.75 for the first $175,000 of value plus $7.75 for each additional $1,000 of value or fraction thereof18
Development Fee Index $250,001 to $500,000Based on project valuation$250,001 to $500,000 $2,984 for the first $250,000 of value plus $7.50 for each additional $1,000 of value or fraction thereof18
Building permit (with or without mechanical) – permit fee and plan review feeBased on project valuationPermit fee 100% of DFI; plan review fee 100% of DFI18
STFI (subject-to-field-inspection) permit – permit fee and plan review feeBased on project valuationPermit fee 100% of DFI; plan review fee 40% of DFI18
Minimum value-based permit or plan review feeMinimum fee$29218
Minimum STFI value-based plan review feeMinimum fee$116.7518
Unenclosed pools accessory to Group R-3 Occupancy–Base fee x 418
Commercial Re-Roofing Permit–Base fee x .518
Permit renewal or reestablishment–1.5 x hourly fee19
Washington State Building Code Council fee (residential building permit)State surcharge$6.50 per residential building permit (+$2 per additional unit in multi-unit buildings)20
Plumbing/Backflow Permit (Public Health – Seattle & King County)Per fixture or item$137 plus $27 per Fixture21
Gas Piping/Medical Gas Permit (Public Health – Seattle & King County)Per fixture or item$137 plus $27 per Outlet21

How to get a building permit in Seattle

  1. Research property information, zoning, and permit history2
  2. Submit preliminary application materials (pre-application) in the Seattle Services Portal2
  3. Schedule an electronic intake appointment (not needed for STFI permits)2
  4. Pay fees once the application is complete2
  5. Plan review; respond to corrections2
  6. Pay outstanding fees and print permit and approved plans2
  7. Request each required inspection4
Apply online
Yes2
Over-the-counter permits
Subject-to-Field-Inspection (STFI) permits for simple projects, issued with minimal review22
Posting the permit
Display permit in a visible location on site23

Permit expiration and extensions

How long a permit lasts
18 months8
Extensions
Renew up to 30 days before the expiration date19

Inspections in Seattle

Seattle’s inspection stages, in order. Do not cover work until the stage has passed (how inspections work).

  1. Foundation inspection (before placing of concrete)4
  2. Framing Inspection (before insulating or covering framing)4
  3. Insulation inspection (after insulation is installed)4
  4. Final inspection4
  5. Same-day inspection if requested before 7 AM4
How to schedule
Online, or 24-hour line (206) 684-89004
Re-inspection fee
1/2 x base fee per reinspection18
After the final inspection
Approval to occupy after final inspection (Certificate of Occupancy may be required for projects other than single-family homes and duplexes)4

Building without a permit in Seattle

ConsequenceApplies toAs the city states itWay to fix it
Civil penalty Seattle Residential Code R103.5Building without a permit24Up to $500 per day24Special investigation inspection before a permit is issued for work already started; special investigation fee may be assessed8
Stop-work order Seattle Residential Code R103.3Starting a building, addition, or remodeling project without a permit24Stop work order24–
Criminal penalty Seattle Residential Code R103.8Violating a notice of violation or order of the building official8Fine of not more than $5,000 and/or up to 365 days imprisonment per violation8–
Investigation fee SMC 22.900B.020.FWork started before a permit (special investigation), value $0–5,000181 x base fee (value $0–5,000); 3 x (5,001–50,000); 5 x (50,001–100,000); 10 x (100,001–500,000); 50 x (500,001–5,000,000); 100% of permit fee over 5,000,00018–
Investigation feePlumbing/gas work done without a permit (Public Health – Seattle & King County)21$273 plus $55 per Fixture/Outlet21–

For how unpermitted work is usually legalized, see how to legalize unpermitted work.

Doing the work yourself (owner-builder)

Homeowner may pull a building permit
Yes8
Homeowner electrical work
Yes25
Homeowner plumbing work
Yes6
Owner and occupancy requirement
Owner must own and occupy the property (electrical work)25

Washington's statewide owner-builder and licensing rules are on the Washington permit guide.

Washington rules that also apply in Seattle

Sources

  1. Fences - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  2. How Do You Get a Permit? - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  3. Contact Us - Hours & LocationCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  4. Construction Inspections - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  5. Plumbing and gas piping - King County, WashingtonPublic Health – Seattle & King County (King County)Checked November 6, 2026
  6. Plumbing and gas piping applications and permitsPublic Health – Seattle & King County (King County)Checked November 7, 2026
  7. Research a Project, Permit, or PropertyCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  8. 2021 Seattle Residential Code, Chapter 1 AdministrationCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  9. Sheds - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  10. Residential Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  11. 2021 Seattle Code Adoption - TimelineCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  12. Building Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  13. Existing Building Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  14. Mechanical Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  15. Fuel Gas Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  16. Plumbing Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  17. Electrical Code - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  18. 2026 Fee Subtitle and related documents (SMC Chapter 22.900)City of Seattle, Seattle Department of Construction & InspectionsEffective January 1, 2026Checked November 7, 2026
  19. Building Permit RenewalsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  20. RCW 19.27.085 Building code council account—Building permit feeWashington State LegislatureChecked November 7, 2026
  21. Plumbing and Gas Piping Program fees (through 2026)Public Health – Seattle & King County (King County)Effective January 1, 2026Checked November 7, 2026
  22. How Much Will Your Permit Cost? - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  23. Construction Permit - Subject-to-Field-InspectionCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  24. Construction Without a Permit - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  25. Electrical Permit - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026