Do you need a permit for a deck in Seattle?

It depends on the project. Seattle exempts some decks from a building permit and requires one for the rest1.

Last checked

On this page
  1. Which permits you need
  2. Limits and conditions in Seattle's rule
  3. Zoning rules: separate from the building permit
  4. What to submit
  5. Who can apply
  6. Deck permit fees in Seattle
  7. Special areas and extra reviews
  8. Who to ask
  9. Deck permit rules in other cities
  10. Sources

Depends on size or scope

Seattle's rule

“You need a permit to build a deck if it is: More than 18 inches above the ground…”1

City of Seattle, Seattle Department of Construction & Inspections, What Permits Do You Need?

Which permits you need

PermitRequired whenThe city’s wording
Building permitMost decks: subject-to-field-inspection construction permitMost decks require only a subject-to-field-inspection construction permit [...]…1
Building permitAddition/alteration construction permit if the deck will be more than 8 ft above the groundYou need an addition or alteration construction permit if your deck meets any of these criteria: It will be more than 8 feet above the ground.1

Limits and conditions in Seattle's rule

Each limit sits next to the sentence it comes from; the conditions in that sentence are part of the rule.

RuleValueThe city’s wording
Exempt up to this height above grade (the wording covers platforms)18 inchesPlatforms, walks and driveways not more than 18 inches above grade and not over any basement or story below.2
Field-inspection (STFI) permit: up to this area750 square feetIt will be over 750 square feet in size.1
Field-inspection (STFI) permit: up to this height8 feetIt will be more than 8 feet above the ground.1
Full permit needed for beams this long or longer14 feetIt includes beams 14 feet or longer.1

Zoning rules: separate from the building permit

A project can be exempt from one and still need the other (zoning vs building permits).

Zoning ruleValueThe city’s wording
Lot coverageDecks more than 36 in above the ground count toward lot coverage (zoning)If your deck is more than 36 inches above the ground: your deck counts toward the percentage of your property on which you can build (called lot coverage).1
Side and rear setbackDecks more than 18 in above the ground: not within 10-15 ft of the front property line or 3-5 ft of either side property line in NR zones (zoning)If your deck is more than 18 inches above the ground: you can’t build your deck within 10-15 feet of the front property line, or within three to five feet of either side property line in neighborhood residential zones.1

What to submit

  • Professional stamp rarely required1

Who can apply

  • Anyone with drafting skills may prepare drawings1

Deck permit fees in Seattle

Fee lines as Seattle's schedule states them. A minimum or base fee is not the whole price when the line says the fee grows with project value.

FeeTypeAs the schedule states it
STFI permit fee / plan review feeBased on project valuationPermit fee 100% of DFI; plan review fee 40% of DFI3
Building permit fee / plan review feeBased on project valuationPermit fee 100% of DFI; plan review fee 100% of DFI3

All of Seattle's fee lines are on the Seattle permit page.

Special areas and extra reviews

  • ECA sites need a pre-application site visit before any construction permit1

Who to ask

Seattle Department of Construction & Inspections (SDCI)4

Building permits

Address
700 5th Ave, Suite 2000, Seattle, WA 98104 (mailing: P.O. Box 34019, Seattle, WA 98124-4019)
4
Hours
Most staff 8 AM - 4 PM (phone or email)6
Inspections
Online, or 24-hour line (206) 684-89007

Deck permit rules in other cities

Rules differ from city to city. Compare Seattle with 18 other cities on the national deck permit guide, or go straight to one:

Sources

  1. Decks - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  2. 2021 Seattle Residential Code, Chapter 1 AdministrationCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  3. 2026 Fee Subtitle and related documents (SMC Chapter 22.900)City of Seattle, Seattle Department of Construction & InspectionsEffective January 1, 2026Checked November 7, 2026
  4. Fences - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  5. How Do You Get a Permit? - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026
  6. Contact Us - Hours & LocationCity of Seattle, Seattle Department of Construction & InspectionsChecked November 6, 2026
  7. Construction Inspections - Construction and InspectionsCity of Seattle, Seattle Department of Construction & InspectionsChecked November 7, 2026